About

Camelot today

For over 50 years, the MIT Outing Club’s Camelot cabin has been a vital resource and center of the club’s activities. Set on about 20 acres near Rumney, NH, Camelot hosts official club circuses, open cabins, and social events and is a base camp for individual club members using the cabin for personal adventures. Camelot sees over 1000 person-nights each year, and many MITOC members are first introduced to outdoor recreation and the club community through Camelot-based events. The cabin is about 2.5 hours from Boston and currently sleeps about 30 people across the loft, living room, and kitchen. To visit, see the Camelot rental page.

Camelot’s loft had to be closed recently because it did not meet modern safety standards; it reopened only after a major repair effort by the cabin managers, and patches like this can only go so far. Making the existing cabin sleep 50 people would mean bringing it up to current code for lodging (sprinklers, fire-rated sleeping rooms, and emergency exits), and the cabin managers and the Town of Groton found no viable way to do that. Building new is the more cost-effective option.

The bunkhouse vision

After over a decade of planning, focus groups, discussions with MIT, and design work by Maclay Architects, we believe that building a new bunkhouse on the existing Camelot land is the best path forward. The new bunkhouse will be sited about 200 meters from the existing cabin and will provide heated sleeping space in a modern, safe, tightly insulated building enclosure.

Who it’s for: The bunkhouse supports MITOC’s goal of making outdoor recreation accessible, especially to new students, with inexpensive, year-round sleeping space that requires no experience or special equipment.

Capacity: The bunkhouse will sleep 50 people (five rooms of 10), enough for all but the busiest weekends of the year.

Amenities: The bunkhouse will have electricity, electric heat, and composting toilets.

Fire safety: A sprinkler system fed by a cistern in the basement, 1-hour fire-rated sleeping rooms, an emergency exit window in every room, and a networked fire alarm.

No kitchen: The bunkhouse will not have a kitchen. Building code requirements would have made including one prohibitively expensive. Instead, the existing cabin, expected to remain usable as a kitchen and lounge for another 10 to 20 years, will continue to be used for cooking.

For more information on the design of the bunkhouse, see Project Details.

The plan

From 2019 through 2021, the Outing Club worked with Maclay Architects to create a bunkhouse design that complies with all modern building codes, is satisfactory to MIT Facilities and the local town board, and yet maintains the wilderness ethos of the Outing Club and its Camelot property.

Timeline

  • 2011: Discussions begin
  • 2013: The MITOC Board of Directors (BOD) approves the project
  • 2014–2018: Focus groups about club needs and the future of Camelot
  • 2018: A generous initial donation in memory of Joris Naiman kick-starts active development
  • 2019–2021: Design with Maclay Architects
  • 2022–2024: Phase 1 fundraising (about $400,000)
  • 2023: The Groton planning board approves the project
  • 2024–2025: Phase 1 construction: a new bridge, off-street parking lot, and access trail, along with the final construction drawings
  • 2026–2027: Phase 2 fundraising, now under way
  • Planned for late Spring 2027: Groundbreaking! This requires raising the full $1.3 million
  • Planned for Fall 2027: Construction complete!

Costs

The bunkhouse project will cost $1.3 million in total, based on 2026 quotes from general contractors for the finished construction drawings.

This includes construction of the new parking lot, which was necessary for Town of Groton approval; construction of the new access trail and bridge, which are necessary for construction vehicles and fire safety; construction of the bunkhouse itself; as well as design and project support work from architects, structural engineers, geotechnical engineers, mechanical, electrical, and plumbing (MEP) engineers, and MIT Facilities.

  • Phase 1 is complete. Donors gave about $400,000 for a completed design and full construction documents for the bunkhouse as well as construction of a new bridge, off-street parking lot, and access trail. Design and documentation included work from structural, MEP, and architectural disciplines and completed a geotechnical site survey. We also made significant progress with MIT administrators and facilities to approve the construction project and plans.
  • Phase 2 is under way. The bunkhouse itself will cost about $900,000.

As of November 2026, $468,000 has been raised by 314 people toward the full $1.3 million. That leaves $832,000 to go, and we need the full amount before we can break ground in late Spring 2027.

Gifts of every size count! Donate online, or read more about costs and funding.

Bunkhouse team

Relaunched in Fall 2026, an eager committee of current MITOCers are spearheading fundraising and current project management! The fundraising committee includes graduate students, alumni, and affiliates who are MITOC trip leaders, board members, and lovers-of-Camelot.

David Lawrence ‘14 (former MITOC president and Camelot manager) and Greg Wallace (MITOC’s alumni liaison), who helped lead Phase 1, remain involved.

We have active participation from the MIT Department of Facilities, the MIT Division of Student Life, and the MITOC Board of Directors. To chat with us directly, reach out over email to mitoc-bunkhouse@mit.edu.